Ripple Carry Critical Path Analysis

MediumLogic CircuitAnalyze1 solved

Arithmetic circuits dictate the maximum clock frequency of an entire chip. The ripple carry adder represents the most fundamental approach to multi-bit addition, cascading single-bit full adders to compute wider results.

A 4-bit ripple carry adder consists of four cascaded full adders. Each full adder computes Sum = A XOR B XOR Cin and Cout = (A AND B) OR (Cin AND (A XOR B)). The inputs are A[3:0], B[3:0], and an initial carry-in Cin. The outputs are S[3:0] and Cout. All 2-input logic gates (AND, OR, XOR) have an equal propagation delay of 1 unit.

Trace the signal propagation through the cascaded stages. Identify the critical path through this combinational logic chain and determine the worst-case gate delay from the arrival of inputs to the stabilization of the final outputs.

Constraints

  • Assume all input signals arrive simultaneously at time t=0.
  • Assume all 2-input gates (AND, OR, XOR) have a delay of exactly 1 gate unit.
  • Fan-out delay effects are ignored.

Topics

timingcritical-pathcombinational-logicadders

Solve this problem

Place the gates, wire them up and watch the signals settle. Every submission runs on the same simulation engine that grades it.

This problem is part of Codiode Pro. The statement above is free to read.

The circuit builder and code editor need a desktop screen. On a phone, read the problem here and open it on a laptop to solve.

Part of Arithmetic and ALU Design

Problem 8 of 32 in the Arithmetic and ALU Design track.

Related problems

Browse all problems · Setup, hold and timing analysis problems · Digital logic design practice problems · Learning tracks

Solve this on a laptopSend yourself the link and continue there.